SAP PS Activity Error Encountered During Period Closing

ggizemkaya
Explorer
0 Kudos
201

Hello, dear colleagues,

I am an SAP PS Consultant. In one of my projects, while performing period closing, I am encountering the error "Actual activity allocation cannot be used." Normally, I would receive this error if the Network Plan is not approved, but my Network Plan is in APPROVED status.

I urgently need support regarding this issue. Please assist me in resolving the problem.

Thank you, and best regards.
Sincerely,

View Entire Topic
RaymondGiuseppi
Active Contributor
0 Kudos

 

So the business transaction RKL 'Actual Activity Allocation' is not allowed for your network in its current status (Message BS 002)

  • Can you check in your system, with BS33 on 'RKL' → Where used icon, for system and user statuses that allow or prohibit the process?
  • Usually 'REL' would allow the process, but some user statuses or custom development may prohibit it?
  • You can also display the information from the display of statuses, click the i info icon.
ggizemkaya
Explorer
0 Kudos
After confirming the approved network plan activity, we check the COFC screen and see that this confirmation is incorrect. While performing the CO material ledger period closing, the closing cannot be completed due to this network plan. BS33 is as follows. Do you have any suggestions?