2025 Apr 22 10:05 AM - edited 2025 Apr 22 10:07 AM
Hello Team,
We have requirement that business team wants Work Approval icon set default at T_code IW31 screen.
Generally, when we tick on permit button and we select the WCD application and after that Work Approval icon will be appears but requirements that can we freeze at main screen without selecting the WCD
Thank You
Request clarification before answering.
Greetings,
you need to assign the work permit to the reference object. When a maintenace order is cretae for this reference object the order inherits the permit which triggrs trhe ""WORK APPROVAL" button.
Alternatively you can assign a WCM default control key to the responsible work center in the reference object.
Best regards, M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.