Situation, I am attempting to setup a gage calibration process in S/4, I have master data setup, I have Characteristic and Measuring Points with upper and lower limit defined. I have general task setup with 24 month strategy pack. What i can not figure out is how to setup a a multi condition strategy to schedule a work order at 24th from last calibration date or when the calipers fall out of tolerance example, I have a digital caliper that needs to be calibrated every 24 months or when measuring tolerance fall out of upper or lower limits... i.e. upper limit is 1.05 mm and lower limit is .99, normal is 1.02.. there is a tolerance +/- .03