Hi all,

I have the following situation:

I have an operation which takes 2 hours. labor time in SAP is set to 2 hours. However, 2 people are working on this operation simultaneously. The total labor time should thus actually be 4 hours. However, total throughput time should remain the same (2 hours).

1) Where can I set the people allocation?

2) How is the costing calculated for these 4 hours of labors?

3) If I change the labor time to 4 hours, how do I keep the throughput time at 2 hours?

I understand these questions are very broad, but any clue in the right direction is highly appreciated!

Michel

former_member27
Community Manager
Community Manager
0 Kudos

Hi Kirpenstein,

Thank you for visiting SAP Community to get answers to your questions. Since you're asking a question here for the first time, I recommend that you familiarize yourself with: https://community.sap.com/resources/questions-and-answers, as it provides tips for preparing questions that draw responses from our members.

For example, you can:

- outline what steps you took to find answers (and why they weren't helpful)

- share screenshots of what you've seen/done

- make sure you've applied the appropriate tags

- use a more descriptive subject line

The more details you provide, the more likely it is that members will be able to respond. Feel free to also take our Q&A tutorial at: https://developers.sap.com/tutorials/community-qa.html

Should you wish, you can revise your question by selecting Actions, then Edit.

By adding a picture to your profile you encourage readers to respond: https://developers.sap.com/tutorials/community-profile.html

Regards,

Dedi

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Michel

Everything is defined at the work center, where you can define different formulas for scheduling, capacity planning and for costing.

In the work center capacity you can define that there are two individual capacities and the duration will be calculated accordingly if you define a formula that considers individual capacities for scheduling.

Take a look into this document that explains the work center setup using standard formulas that might help you:

https://archive.sap.com/documents/docs/DOC-52403

Regards,
Caetano