on 2025 Feb 11 4:45 PM
In SAP PM module
After TECO'ing the order if we try to do any changes in the order we must get a BS013 informative message stating that the order is in Teco'd status
But in our case BS013 is already written in the abap logic but still error is not thrown after changing of dates even after Teco'ing .
Can you suggest me why SAP is not throwing error?
Request clarification before answering.
Hello yathiraj,
can you please explain the scenario because mostly after performing the confirmation the system will make the fields as greyed out and no further changes can be made only the settlement rule can be changed , whereas if you want to perform or make changes in the order level then you need to cancel the confirmation.
so can you please explain what is the error that you are facing .
Regards,
Neeraj.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 30 | |
| 27 | |
| 21 | |
| 4 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.