Hi,
We want to place sales orders assigned to WBS in our SAP S4Hana Cloud. We currently have scope item J59 activated in our S4 Hana Cloud system. Do we need to activate another Scope Item to be able to create SO assigned to WBS Elements?
KR,
Jose
Dear Jose,
please consider the following scope items that should cover your request:
- EPPM accounting via "Sales Order Processing with Project Account Assignment (4I9)": https://rapid.sap.com/bp/#/scopeitems/4I9
- The corresponding Revenue Recognition part is available via "Event-Based Revenue Recognition - Project-Based Sales (4GQ)": https://rapid.sap.com/bp/#/browse/scopeitems/4GQ
Best regards,
Franco Schletter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Here are some SAP resources you may review based on your topic "activate | wbs element | wbs | wbs elements | sales orders | sap s4hana cloud | s4 hana cloud system | scope item"
Best Practices for SAP S/4HANA Cloud
The SAP Best Practices for SAP S/4HANA Cloud can enable you to improve: ... Accounting for Incoming Sales Orders - This scope item provides a report of all ... from SAP S/4 HANA Cloud to SAP Business Suite or SAP S/4HANA system. ... for employees to record time for WBS elements, cost centers, and internal orders.
https://support.sap.com/en/product/best-practices-s4hana-cloud.html
Customer Projects Migration - Part 1: Migration of Fixed Price ...
Sep 20, 2019 ... General SAP recommendation: close projects in legacy system and create only new projects in SAP S/4HANA Cloud ... Project in Stage ?In Execution?; Work Packages / Work Items; Activity / Expense Planning; Sales Order Header / Item ... Code e.g. A0; Select WBS element of the dummy migration project?...
Activity Types and Service Materials for Project Services
Aug 18, 2019 ... To enable activities to be planned and allocated, quantities of output are ... Within S/4HANA Cloud it is best practice that activity type and sales ... SAP Best Practice : Sales ... to set Activity Type and Material ID and Description to the same wording ... Work Item; WBS Element (Work package not Billing Item).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The fields Profit Center and WBS Element are available in the migration object 'Sales Order (only open SO' ) - 'Item' - Account Assignment.
[View Article](https://answers.sap.com/questions/13238935/view.html)
I hope this answered your question! If it did, please mark it as the 'Best Answer' so I can continue learning and answering questions in the community.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
8 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.