Dear, 

I have a scenario where a contract with a quantity of 1,000 was created.

I am currently able to create a sales order with reference to the 1,100 contract, for example.

How can I lock this amount via configuration?

I need to allow order creation with reference only up to the contract quantity in this example quantity of 1,000.

Thanks.


Accepted Solutions (0)

Answers (1)

Answers (1)

Samaun
Explorer

Hi There,

go to Transaction VOV7. Check completion rule setting and use appropriate option for your requirement.

Tadeu_Olivera
Discoverer
0 Likes

Hi Matsikun, 

Thanks for your message.

But, I tested with this option in VOV7 edit than C for B but unsucessefull in this change.