on 2016 May 06 7:49 AM
Hello Guys,
My requirement is we have to use sales BOM in Quotation to get costing.
sales order created with different qty and material BOM created with different quantity.
Now the requirement is Sales BOM should consider only in quotation and sales order.
but when we run MRP with MTO it should consider Material BOM to generate planned order and PR.
Please suggest any solution.
Hello,
Issue has been resolved now,
what i done, i created costing BOM and Material BOM separately so now system consider the costing BOM during the Quotation and during the MRP run system is consider the material BOM to calculate the stock requirement.
Thank you...R.Brahmankar..