Hello Experts,
can someone help me to check how to figureit out configuration for saftey time in Mrp 2 view in material master .
can we increase limit from 2 digits to 3 digits in mrp view .
Request clarification before answering.
Hello @jerrysam
Safety time is defined with the SHZET data element:
Two digits, i.e. up to 99 workdays is more than enough. I think something must be seriously off in your MRP planning if you need more than that.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @jerrysam
The length of the safety time field is not customizable. Theoretically, but just theoretically, you could change the data element to 3 digits. However, it will lead to mass regeneration of dependent objects. If you are extremely lucky, that will not break down the system. Most probably it will. Such a disaster won't be covered by SAP maintenance. So when you ask SAP support for help, they will issue a fat bill, once they stop laughing.
There is the note 2422504 - MM02: Increasing the MARC-SHZET field length telling basically the same.
You could add a custom field for longer safety time as indicated in the note 44410 - Integrating customer-specific fields in the material master. But then you would need to modify standard MRP logic to use the custom field instead of the standard one - check the documentation to the configuration node Production -> Material Requirements Planning -> Business Add-Ins for Requirements Planning for details on MRP enhancements.
Best regards
Dominik Tylczynski
User | Count |
---|---|
95 | |
12 | |
10 | |
8 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.