S4HC public manufacturing- Information msg while creation of production version

Adventurer
Participant
0 Kudos
520

Hi all,

in S4HANA Cloud Public, I received an information message while creating 2nd production version for a finished material.

As you can see, task list exists, but why system generated this information?

I know I can pass and save it, but in my opinion this msg is wrong.

BR,

Amin

View Entire Topic
Matt_Sui
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi 7ca3e57e-d46d-47f1-a399-d3d21d513f67,

The error is due to the wrong group counter of the routing.
Although it is shown in the frontend as "1", it is actually stored as "01" in the backend table (2 digits with leading zero). So, the system is actually serching for the task list "N / 50000001 / 01". It is very likely that your currently routing group counter is stored as "1" in the database, which is wrong. I don't know how the wrong data is created, actually I have found a similar issue as yours from other users.
So my suggestion is to delete and re-create the routing and then create the production version again.
If the issue still persists, please open a case in component PP-PI-MD-2CL so that we can check the data in your system.

Best Regards,
Matt

Adventurer
Participant
0 Kudos

Hi matt_sui,

When I put 01, the system will automatically change it to "1" and again error message.

I will create an incident for it.

Thanks

JulianoRomanato
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello 03221991

How are you? I have accepted matt_sui's answer for this question, as he answered for more than 7 days ago and there is no answer from your side. If you do not agree, you can open again this question.

Regards.

Juliano Romanato.