Hi,
we use S4H with ePPDS. the rework process is done by entering a rework operation with control key PP_98 where the rework is set. the only problem is that the rework ticked in the control key means that the operation is not scheduling relevant, and I guess this is why the operation is not coming through to ePP/DS?
My question is how can I make the rework process with the rework operation work so that the operation arrives in ePP/DS?
Kr,
Walter
Request clarification before answering.
Hello,
You will have to use CIF Enhancement CIFORD04 to transfer Rework Operations in PPDS
Regards
Gaurav