S4Hana rework process with ePP/DS using rework operation

ws
Participant
0 Kudos
995

Hi,

we use S4H with ePPDS. the rework process is done by entering a rework operation with control key PP_98 where the rework is set. the only problem is that the rework ticked in the control key means that the operation is not scheduling relevant, and I guess this is why the operation is not coming through to ePP/DS?

My question is how can I make the rework process with the rework operation work so that the operation arrives in ePP/DS?

Kr,

Walter

Accepted Solutions (1)

Accepted Solutions (1)

guglanigaurav198768
Product and Topic Expert
Product and Topic Expert

Hello, 

 

You will have to use CIF Enhancement CIFORD04 to transfer Rework Operations in PPDS

https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/7939c95360267614e10...

guglanigaurav1987_0-1710220795987.png

Regards
Gaurav

 