on ‎2022 Feb 18 3:06 PM
Dear PP Gurus,
We are planning to implement PMRP in client.
When we are releasing the simulation,
It is just copying PIR version 00 which we used as reference for simulation to version 01 when we release the simulation.
Can you advise us what is missing in PMRP simulation?

Request clarification before answering.
Hello
Currently, Predictive MRP will only update the Planned Independent Requirements when you release a simulation.
According to the roadmap published by SAP (https://roadmaps.sap.com/) the automatic adjustment of changes in the work center capacity is planned for Q4 of 2022.
Regards,
Caetano