S4Hana -PMRP Simulation release does not update source of supply/pre production in MD63

0 Likes
1,036

Dear PP Gurus,

We are planning to implement PMRP in client.

When we are releasing the simulation,

  • After splitting the source of supply for FG material in process simulation app, system creates PIR quantity with version 01 but does not update PV as per split in simulation summary.
  • Preproduction is also not updated in the PIR Version 01.
  • Change in capacity values also not reflecting in work center.

It is just copying PIR version 00 which we used as reference for simulation to version 01 when we release the simulation.

Can you advise us what is missing in PMRP simulation?

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

Currently, Predictive MRP will only update the Planned Independent Requirements when you release a simulation.

According to the roadmap published by SAP (https://roadmaps.sap.com/) the automatic adjustment of changes in the work center capacity is planned for Q4 of 2022.

Regards,
Caetano

taras-tymofii
Explorer
0 Likes

Hello Caetano,

I'm facing the same issue.

Could you please inform if work center capacity adjustment works now? and Where I can find proposals?

Thank you in advance.