on 2021 Nov 08 6:02 PM
Dear All,
Can you let me know the table for Cost element master data with material code reference?
Thanks & Regards
Request clarification before answering.
Hi joao.dias1175_5
For Cost Element, you can look at CSKB.
For Material number, MARA will give you that.
Expanding the topic on the mechanics of it, usually, the cost element is derived from the valuation class of the material master. If there is any valuation class in Project valuation class field of material master, a G/L account is assigned in transaction OBYC. Otherwise, cost element for the valuation class will come from the valuation class field of the material master.
Hope it sheds a light. Kindly accept the answer if it helps to address your topic.
Cheers,
Luis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
13 | |
11 | |
5 | |
5 | |
5 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.