on 2024 Feb 02 1:55 PM
Dear SAP Community & MRP expert!
I am running MRP live (with Advanced planning - PP/DS) in S/4HANA 2022 FPS02 version and we are struggling to understand how does SAP works for External procurement proposal :
Here an example from Material Coverage: Requirement is for the 25.06, but the purch. Req is placed 1 days AFTER ?
Then, Material Coverage apps, request to manage this “shortage” and make a proposal to advance the Purch. Req of 1 day. Of course!
PS : my Purch.Req is not fixed, and I am not using TimeFence. So, I am expecting the MRP live to reschedule it here automatically.
In PP/DS RRP3 we can see that the PurRqs is well scheduled …
I am struggling to understand the logic of these proposal :
Is there any master data or customizing that could influence this scheduling issue ?
Thanks!