S/4HANA Material Coverage apps and Shortage logic

Louis-Nicolas
Participant
0 Kudos
201

Dear SAP Community & MRP expert!

I am running MRP live (with Advanced planning - PP/DS) in S/4HANA 2022 FPS02 version and we are struggling to understand how does SAP works for External procurement proposal :

Here an example from Material Coverage: Requirement is for the 25.06, but the purch. Req is placed 1 days AFTER ?

LouisNicolas_0-1706881960083.pngLouisNicolas_1-1706881968390.png

Then, Material Coverage apps, request to manage this “shortage” and make a proposal to advance the Purch. Req of 1 day. Of course!  

LouisNicolas_2-1706881991627.png

PS : my Purch.Req is not fixed, and I am not using TimeFence. So, I am expecting the MRP live to reschedule it here automatically.

In PP/DS RRP3 we can see that the PurRqs is well scheduled …

LouisNicolas_3-1706881991630.png

I am struggling to understand the logic of these proposal :

  1. Why does a planner should fix this kind of planning/scheduling issue ?
  2. What does a Shortage is triggered in this case (I means why not automatically rescheduled)
  3. Also, why does the others PurReq / DepReq for July are well scheduled  ?

Is there any master data or customizing that could influence this scheduling issue ? 

Thanks!

Louis-Nicolas
Participant
0 Kudos
Up! Does someone have an answer ? Else I will open a Case to SAP...

Accepted Solutions (0)

Answers (0)