is it possible if i maintain one control key ( ex. PP01 ) for all operations in the routing? this control key has automatic goods receipt checked. is it logical that everytime i confirm an operation, a GR (101) would occur?
or should i maintain only 1 operation whith auto GR (the last) one, so upon confirmation only would the GR occur
Request clarification before answering.
Hi
It is better to maintain control keey with auto GR for one operation i,e for the last operation as it will be logically also correct , as we receive the finished product only once after compelting the operations .
Regards,
Mallikharjun.