on 2021 Oct 19 2:27 PM
Dear experts,
I´m searching for an option to use one line in Routing CA03 only for the backflush - which is on our site based on preliminary cost estimate MF30 but it should not be part if the Material cost estimate created with CK11N or CK40N.
The costing relevancy is not helping here as it´s changing both.
Thanks for input upfront.
Best Regards
Sebastian
Request clarification before answering.
Hi,
If by line you mean sequence
Costing happens with 0 sequence, you can add your line to second sequence
if you mean routing as line
create two Production version with same validity and lot size (both should be valid at once)
to the first PV(sorted by verid) assigned to costable routing
to the secont PV assign the non costable routing
both the option, will not accect the planned cost but will affect the actual cost.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
15 | |
8 | |
7 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.