on 2019 Feb 21 3:30 PM
Hello VC Community:
I am testing the Order BOM functionality in Variant Configuration for a client. I created the BOM and Routing using the Engineering Workbench (CEWB) with a change number that has parameter effectivity assigned. I have set some simple dependencies for BOM component selection and operation selection. When I execute CU51 my BOM components are selected as expected but when I click on the icon to display the task list for my Routing, I get a message stating "No task list found for material XXX plant XXX".
I also noticed that when I view my VC model in transaction PMEVC, if I select the menu path 'Environment > Object maintenance > Routing maintenance' it takes me to 'CA02'. Since my Routing was created via CEWB it tells me no task list exists if I press 'Enter'.
Does Variant Configuration have some challenges dealing with BOM and Routing objects created via CEWB using change numbers with parameter effectivity ?
Request clarification before answering.
Korrection, the note is 1944995.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
9 | |
9 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.