Former Member
0 Kudos

hi,

can any one give me the complete flow with transaction code for rework process manualy,and also by using trigger points

regards,

saravana

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member184627
Active Contributor
0 Kudos

Hi,

In the tigger point you have given system status as PCNF.So when this status is reached trigger point will work.

So confirm your operation partially.

Regards,

Senthilkumar.

Former Member
0 Kudos

Hai Senthilkumar SD

This there any technic to make default as Partical confirmation while using the T-code CO11n

Regards,

Leo

former_member184627
Active Contributor
0 Kudos

Hi,

This setting is maintained in the confirmation parameters (Transaction OPK4).

Select the confirmation type which needs to be proposed during confirmation.

Regards,

Senthilkumar SD

Former Member
0 Kudos

Hai ,

  I ask you that how to maintain default as Partial confirmation in CO11N

Here if i open CO11N system made default has final confirmation,  I know we can change to Partical confirmation, It mite happen by mistake i confirm the order with final confirmation because it is in final confirmation  but i need to confirm partially ( I am Trying to say that instead of final confirmation i need to make partical as default)

Former Member
0 Kudos

Are you asking about rework production order creation?

Former Member
0 Kudos

Hi,

1. First create a Reference op set in tcode Ca11.

Enter the plant,Description , usage and status

for the ref op set

Enter lotsize and unit of measure.

Enter the op as 0010 / workcenter/op control

key/Description for the op

Enter the standard values and save.

2. Create a Standard trigger point in CO31.(Ex

Production)

Enter the Trigger Point usage /Group as FERT.

3.Tick the Trigger Point Functions.

4. Enable the indicator create order with Reference .

5.Enter the system status as PCNF.

6. Enter change as +.

7. Enable the indicator once.

8 . Now place the cursor on the create order with reference.

9. Goto Parameters.

10. In the Parameter enter in the group the created Reference op set group no.

11. Order type as PP01 and group counter as 1 and save the Trigger Point.

12. Now goto the Routing for your Material.

13. Choose the last op to assign the Trigger point.

14 .Select the OP -


> Goto ---> Trigger Point overview.

15. Enter the Trigger Point usage as FERT.

16.Now choose that line ,select the Details---> Trigger Point

17. The system will says standard trigger point exists from which you can

select the created Trigger Point (EXx Production)and save.

18. MD02/MD04.

19. Convert the Planned Order into Production Order and Release the order.

20 .Now confirm th ops.

21. For the last op enter the yield and rework qty

and set the status as PCNF.

22. If the status of last op is PCNF then in the

system a POP UP will appear as Activited by

Trigger Point /Create order with reference/order

number/sequence and op number which trigger point

works and enter.

22. Now a rework order will be created.

23. In c003 enter the number which is next to the actual prodn order no.Rework

order will be seen.

Pls reward if you found useful

Regards,

nandha

Former Member
0 Kudos

hi nandha,

during confiramtion,it is not triggering that is the main problem, occurs to me

regards,

saravanakumar

Former Member
0 Kudos

in trigger point change

see the setting\

usage = trigger point

function

create order w/ reference

Once - tick is not activesystem ststus - REL/PCNF

change = *

Actiated = 2

it will work if you have this setting, i hope you have assigned this trigger point in operation.

Former Member
0 Kudos

Hi,

While assigning the trigger point usage FERT <b>check whether you have enabled the indicator for functions.</b>

Award points for useful answers and then close the thread

Regards,

nandha

Former Member
0 Kudos

Hi to all,

settings are same as u people told,during confirmation the yeild qty is 500,if i put rework qty as 32, it will automaticaly trigger no, but it is not working so.wat will be the problem. i ahve created trigger point with usage functions Create order with reference,Insert reference operation set, both i used,initialy i used iInsert reference operation set,1y.after then i changed by using both the function.

regards,

saravanakumar

Former Member
0 Kudos

U just enter the data what I have specified

1) Trigger point usage -


0004

2) Click on trigger point functions

3) Click on create order with reference

4) System status enter CNF

5) Change --- (- Reset status)

6) Activate function – function is activated by staus and manually

7) Pop up screen appears enter the ref operation number and Rework order type

And group counter

8) go to routing select operation and assign trigger point

9) at the time of confirmation it will ask u the weather u want to trigger for rework there u select and press yes it will go for the rework production order.

10) U go co02 and check the next production order, the rework order quantity with display,

reward point if it is usefull

Madhusudhana.M.A

Former Member
0 Kudos

Hi madhu,

during confirmation, if i enter the PO number, it will automaticaly took that yield quanty and display, if i am entering rework quantity, there it is saying confirmed qty is greater than over delivery tolerace limit, in warning msg,but ther is no triggering point effect is happened, after then what i have to do, wether i ahve to confirm, r i have to reduce the yield qty and cofirm that order raaa.......if so means,then were i can see the rework order, can u explain the next step

regards,

saravanakumar

Former Member
0 Kudos

Hi nandha,

In that production order wer we can see that rework order, after then wat is the next step, tel me clearly by step by step process,from that production order to confirmation, GR,how it will be done for that rework

regards,

saravana