on 2021 Oct 10 8:25 AM
hi
our financial team create subsequent debit in po item after that buyer return a part of po item to vendor with old price in purchase order ( at first , invoice canceled by credit memo with the return quantity )
FI team need that vendor be debited with new price automatically ( by considering subsequent debit )
ho can we handle this issue ?
Request clarification before answering.
Hi,
Can it possible that you can create return Order with new Price , so its all subsequent transactions will be okay, as per new pricing.
Bhumika
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Why subsequent debit for PO if vendor return an item of PO?
If invoice was created for all items and credit memo in MIRO is an option for that item of that PO after return.
If in case mistakenly subsequent debit for PO created - try to cancel with MR8M for that document number but why a new price and where needed in document to post?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks for your reply
You need to revisit the steps and check accounting entries at the end, if not matching - you need remap the steps
1. If invoice was created for all items and one item need to return.
2. Create return delivery for that item of PO
3. Credit memo in MIRO for that item of PO
( no need of subsequent debit for PO)