on 2022 Jul 28 5:11 AM
Hi, SAP Gurus.
Good day!
I have already created a Resource Network in /SAPAPO/RESNET but I could assign them in the Advanced Planning Tab in Material Master (MM02). In SCM version of PP-DS, we can assign them through /SAPAPO/MAT1, but due to the simplification of S/4HANA, product-location maintenance should be done in MM02, thus, most of the fields (including resource network) are grayed out in MAT1.
Hoping you could help me with this issue I am encountering.
Thanks!
Best Regards,
Dave
Request clarification before answering.
I have resolved the issue myself. We have to assign the Resource Network first to the Planning Version before we can assign it to the Material Master. In my case, it took a few minutes of waiting time for it to take effect.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
8 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.