on 2016 Apr 08 11:10 PM
Hi everyone.
This is a fresh instalation for SAP S/4HANA on premise 1511 and I'm facing following issue:
When I'm trying to run t code MD01 for Total Planing, system is picking following error:
Requirements planning is not active in plant 1000.
When I try to create planning file with t code MDAB, that runs correctly but no materials are included for planning.
I'm stuck in this point.
Please advice
Thanks!
BEst Regards.
Juan.
Request clarification before answering.
Go to transaction OMDU and set the box on the second option Material requirements planning.
THis solution worked