on 2024 Jun 21 1:45 PM
Hi,
I have the following requirement - components are assigned to operations in my routing. Lets say one component is assigned to operation 0200, because the consumption posting should be done via confirmation of operation 0200 and backflush setting. BUT the requirement date of the component should be the one of the operation 0100 just before? Is that possible in any way (also via badi or enhancement)? The offset time in BOM does not really help as it is a fixed value.
BR Christian
The requirement date of a component is determined by the operation to which it is assigned. If a component is assigned to operation 0200, its requirement date will be based on the scheduling of operation 0200.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
111 | |
9 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.