on 2022 Nov 11 5:16 PM
How does the follow-up concept work in case of reorder point planning? Both are externally procured materials and MAT-B is follow-up of MAT-A.
MAT-A
Reorder point - 10
MRP Type - VB
Stock level - 0
Fixed Lot - 10
MAT-B
Reorder point - 20
MRP Type - VB
Stock level - 0
Fixed Lot - 10
Will the system transfer the need of MAT-A to MAT-B?If so, what will be the output of MRP? Will it create PR's based on MAT-A or MAT-B?
Request clarification before answering.
Hello
As explained in SAP Note 43636-Discontinuation control, discontinuation only works with MRP Type PD, so you cannot use MRP type VB here.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
62 | |
9 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.