REM PRODUCTION IN MFBF SCREEN

0 Kudos

Parallelization type of confirmation processes not yet defined Message no. RM780

I HAVE SOME OF THE ANSWER BUT THAT COULDN'T HELP SO I AM POSTING ISSUE

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

For your REM profile (assigned in MRP 4 view) check it's customization in OPS2 for Process control. If you have used the Process control in your REM profile. Please check process control key in the OPKD Customizing transaction. It is used with the confirmation for example, separation of the backflush.

If you need the process control key then Define Paralleling Type for Confirmation Processes in OPKB if not remove the Process control.key from Rem profile.

Best Regards,

R.Brahmankar

0 Kudos

issue.png

that (beside item column right) tab is fixed tried to change but unable to do this ( that is 1 for pm/pp-pi and 2 for pp-rep) but 1 is non editable mode

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Sorry did not get you? Please share screen shot.

Best Regards,

R.Brahmankar

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Screen shot is from OPKD or OPKC?

As I know OPKD is for REM and OPKC for Discreate and Process orders.

Best Regards,

R.Brahmankar