on 2022 Mar 23 8:39 PM
Hi Experts.
1. MRP is planning a "Test" material. Material is configured as:
External Procurement, Demand Driven Planning
Lot-forLot
ATOS_CPC - All demand consumes current forecasts:
2. There is a Demand Plan released for this material for 100 ea every month and a Sales Order for 67 ea that needs to be delivered by July (guess today is March), and no stock available:
3. When i execute Run Planning (MultiBom Level and allowing Planning Proposals in the Past) i get a purchase proposal by 100 for every month, except in July that there are two, one by 67 for the Sales Order Demand and one by 33 for the rest of the forecast (100 - 67 = 33):
Actually, for us, only the Sales Order is real demand and we want to by this items now (March) even if the delivery is planned for July.
Is there anyway to automatically release only proposals for April and the one by 67 ea coming from SO in July avoiding the propsals for April, May, June and July coming from Forecast?
Looking Forward to hearing from you
BR
Request clarification before answering.
User | Count |
---|---|
126 | |
9 | |
8 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.