I am using function module MD_STOCK_REQUIREMENTS_LIST_API for generating a report.

I am condused about how to link the production order or planned order or purchase requisition with teh dependent requirement. All my materials having teh lot size as EX. When I run the function module I could see many dependent requirements and planned order or purchase requisition. then how to link this with dependent requirements using the function module MD_STOCK_REQUIREMENTS_LIST_API.

Please guide.

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hello

You should take a look on the following note, regarding the pegged requirements on MRP:

12955Pegged orders/pegged requirements: Documentation

The note itself is about MD09, however, the information below is specifically relevant, as it describes the system design:

"The respective current data on stocks, issues and receipts of the

materials in question is evaluated in the pegged requirements display.

There is no index that the system could use to determine which issue

element (sales order, planning, reservation, dependent requirement, ...)

is covered by a certain receipt element (purchase order, production

order, purchase requisition, planned order, stock level ...)."

BR

Caetano

Answers (1)

Answers (1)

sjeevan
Active Contributor
0 Kudos

If your client's process is not MTO with dependent requirement having sales order account assignment, then linking would be pretty hard, you can try based on requirement date though.

Former Member
0 Kudos