on 2008 May 16 11:54 PM
Hi
Is it possible to process the rejected RFQ?When I opened my document over view I noticed that the rejected RFQ also listed there and I could easily adopted it in the PO.Please Comment
Request clarification before answering.
Hi Sam,
Generally a Po should not be created when a RFQ is rejected however sometimes we would be aboe to create it
check the System messages for it
Go to SPRO-> MM-Purchasing -> Environmental data -> Defineattributes of system messages -> Select system messages -> click on position
Give Ver 00- Appln 06- Message 434 "This quotation item already rejected" Change the category from "W (Warning )" to "E" error. Then at the time of creating PO you will get error message.
So you will not be able to create a PO for RFQ which is rejected
It was the system message which is allowing it to create PO for rejected RFQ's
try making these settings and generate PO for a rejected RFQ
Hope this will solve the issue
In case of any more clarifications required do get back
Reward points if it is helpful
Regards
Pavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
rejected RFQ means you have already communicated the rejection message to the Vendor ...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
12 | |
10 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.