on 2023 Oct 02 2:50 PM
Hi Guys,
So I am testing the concept of multiple specifications for an implementation. I followed all the steps, and during result recording I am observing that both of my MS points show a failed result. As per the specification limits one of them should have passed:
As you can see, for 'Content 38%', the reading of 6 should have been within its limits of 5 to 7. Still it is valuated as a Failed result. Any guesses why?
Regards,
Nihal.
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Dear Nihal Nayak,
thank you for the details provided.
It worth to check the relevant KBA in the topic:
3022513 - Multiple specification object is not valuated in results recording transaction (for example: QE51N)
Have a nice day,
Albert
***
Read and follow the 'SAP Community Rules of Engagement' at
https://www.sap.com/community/about/rules-of-engagement.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Albert. I followed this KBA and maintained a sampling procedure with appropriate valuation mode for automatic valuation, and it worked!
Regards,
Nihal.
User | Count |
---|---|
89 | |
12 | |
7 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.