on 2018 Jun 17 5:23 PM
Dear All
I have been going through the this forum for understanding how to inmplement Individual capacity functionality for production order. but some how no thread provides the complete details.
I have a scenario of cellular mfg. where similar machines are clubbed together. I understand this can be achieved by Individual capacity functionality. But need steps involved to implement the same.
I will appreciate if some document or step by step approach can be provided.
I am also adding a detail of the query as well
" We have work center say XYZ where I perform milling operation. I have 3 milling m/c say 001,002,003. I have operation quantity is 150 piece.I want to specify that 40 pieces are to be processed on machine 001, 60 pieces on machine 002 & 50 pieces on machine 003.
How I can allocate this.Please help out.If possible please tell step by step procedure"
Regards,
Vivek
Request clarification before answering.
Hello Vivek,
"capacity category doe not exist" happens in production order can be caused by customizing for scheduling. Please check in OPU3 for the combination of plant and order type, then under tab "Detailed scheduling", is "scheduling" and "Generate Capacity Requirement" ON?
best regards,
Jessica Li
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.