Hi PPDS experts,

If I Plan and schedule FG in PPDS, but plan raw materials in HANA..how do we change the dates of raw material purchase reqs based on the new scheduling dates of finished goods in PPDS..

If I use PPDS for both FG and raw materials, I can run top down heuristic to align the whole BOM chain based on my FG new scheduled date..but if I use HANA for raw materials, how do I get the visibility to change raw material procurement dates as the FG scheduling dates have been changed in ppds?

@tiago_furlanetto @yasmin_alayyan 

 

 

Accepted Solutions (0)

Answers (2)

Answers (2)

guglanigaurav1987
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Swathi, 

 

This functionality is part of standard S/4 HANA Planning with PPDS. Have you gone through this help document?

https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/aa35c95360267514e10...

Regards

Gaurav

swathi_rege
Active Participant
0 Kudos

Any insight?