on ‎2023 May 29 10:57 AM
Dear SAP Gurus,
Scenario:
MIC s need to be created across several plants for the business. But the MIC s remain the same regardless of the plant in which MIC is defined. ( Values, Attributes no change)
Requirement:
Define the MIC in only 1 plant so that Master Data management is lean and simple- Changes to MIC to be made , if required, in only 1 plant
Query:
Is it possible to define a reference QM plant say QM00 and assign every individual Logistics /Mfg. Plants where QM is active , to this QM00 ref. plant?
This way , MIC s need to be defined in only 1 ref. QM plant QM00 . Any changes etc to MIC will be performed in the QM00 plant Only. Due to the assignment. it applies to all individual Logistics /Mfg. Plants and can extend to Inspection plans as well
Pl note that Client using RISE with SAP S/4 HANA Private Cloud version 2022 .
Pl advise asap
Thanks
Ranganath
Request clarification before answering.
Hello Rangnath,
Hope I understood query correctly
Your scenario can be managed ,
MIC to be created only in one reference plant
reference plant MICs to be used in any other QM plant's inspection plan ,
it is standard and no other customizing or enhancement needed
also no need to set relation between reference MIC Plant and QM plant
Best Regards,
Milind
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 33 | |
| 17 | |
| 14 | |
| 13 | |
| 9 | |
| 4 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.