For a particular Material, we need to assign 5 Storage bins.

When we create a Transfer order after the Good receipt process; the system should automatically suggest the first Bin.

And if the first bin is full, system should automatically suggest the next bin based on the bin capacity. Error should be generated if we try any other bins other than the assigned ones (5 bins).

Is this possible in SAP WM? Or EWM? What all configurations are required for this requirement?

Accepted Solutions (0)

Answers (1)

Answers (1)

MohdRashid
Active Contributor
0 Kudos

HI 

 

For EWM, YOu use fixed  bin startegy and assign five fixed bin so it will work go throug  the thread. It will help you

https://community.sap.com/t5/supply-chain-management-blogs-by-members/fixed-bin-concept-in-sap-wm-vs...

 

For WM, 

Here  I would suggest you to do POC. Have a strategy next empty bin and addition to existing and create five bins in one storage section and determine it and maintain indicator in material master . then do the test I hope it will work. 