For a particular Material, we need to assign 5 Storage bins.
When we create a Transfer order after the Good receipt process; the system should automatically suggest the first Bin.
And if the first bin is full, system should automatically suggest the next bin based on the bin capacity. Error should be generated if we try any other bins other than the assigned ones (5 bins).
Is this possible in SAP WM? Or EWM? What all configurations are required for this requirement?
Request clarification before answering.
HI
For EWM, YOu use fixed bin startegy and assign five fixed bin so it will work go throug the thread. It will help you
For WM,
Here I would suggest you to do POC. Have a strategy next empty bin and addition to existing and create five bins in one storage section and determine it and maintain indicator in material master . then do the test I hope it will work.
Regards
Rashid Khan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
15 | |
9 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.