on 2025 Oct 15 12:49 PM
Hi Experts,
I believe that Advance STO in s/4hana public cloud does not currently support the use of Purchase SA (scheduling agreements). Do you know whether this functionality is planned to become available in future releases ?
thanks and regards
A
Request clarification before answering.
Thank you for your question.
Yes, you are right. As of the current public cloud edition, the STO process does not support purchase scheduling agreements.
What is supported as of today is the Advanced Intercompany STO, which covers Sales/Purchasing orgs in different companies with Purchase Orders but not scheduling agreements.
Although purchase scheduling agreements are available in public cloud for standard procurement, the same functionality is not yet integrated into the Advanced Intercompany STO process.
At this time SAP is yet to publish any roadmap item or feature note that confirms when or whether this integration will be delivered in future releases.
You may consider raising this on the SAP influence page if this is critical to your busines/project.
Let me know if you have any questions.
Best regards
Chris
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 32 | |
| 18 | |
| 15 | |
| 14 | |
| 9 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.