Hello Guru's,

I have a material which is set G3 status (Discontinued) in Material master MRP views, but still system generating the Purchase requisition and dependent requirement after MRP run.

it is a phase out code we will not produce it. 

please help me to resolve the issue.

nidhi123_0-1716530433318.png

below u can see the details for G3

nidhi123_0-1716540480536.png

 

thank you in advance

View Entire Topic
matjazmoser
Active Participant
0 Kudos

Greetings,

I suggest do delete the PR item for this material and change message types from warnings to errors. Run MRP and see if any combination meets you requirement.

matjazmoser_0-1716795080677.png

Best regards!

 

nidhi123
Explorer
0 Kudos
HI, i am not able to do customization because it is production server. is there any other ways to stop the automatic creation of purchase requisition after MRP run for that material?
matjazmoser
Active Participant
0 Kudos
Greetings,