Hello Guru's,
I have a material which is set G3 status (Discontinued) in Material master MRP views, but still system generating the Purchase requisition and dependent requirement after MRP run.
it is a phase out code we will not produce it.
please help me to resolve the issue.
below u can see the details for G3
thank you in advance
Request clarification before answering.
Greetings,
you can try setting MRP type to ND at material master MRP 1 tab.
Best regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Greetings,
I suggest do delete the PR item for this material and change message types from warnings to errors. Run MRP and see if any combination meets you requirement.
Best regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Greetings,
it is possible that you defined the status after the dependant requirement was set in that case the system planned procurement for discontinued material.
Can you perhaps share a screenshot with details of G3 status customizing?
SPRO -> Logistics - General -> Product Lifecycle Management (PLM) -> Material Master -> Settings for Key Fields -> Define Material Statuses
Best regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 32 | |
| 18 | |
| 15 | |
| 14 | |
| 9 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.