purchase order delivery date is same as creation date

former_member311909
Participant
0 Kudos
264

Hi,

For one of the plant.when PO is created manually delivery date is taking same as creation date.why it so.

Can any one provide the reason.

There are no Personal settings in Purchase order

for the material the data maintained as follows :

MRP2 :

Planned delivery time is 24 days

GR processing time is 5 days

Purchase info record :

Planned delivery time is 24 days

SPRO-Plant parameters

Purchase Processing time 1 day

Regards,

somiraghu

View Entire Topic
former_member204661
Contributor
0 Kudos

Hi,

This should not happen, the planned delivery time should have been added to the creation date, kindly check up with ABAP, whether any code has been put in place, for this scenario.

Regards

Shailesh