Hello - We have a requirement to pay Royalty to a Vendor based on the number of units sold. For example:

  • pay the vendor $1/unit invoiced
  • 2500 units invoiced for that calendar period
  • However the negotiated contract with the vendor states we need to pay a minimum of $3000 per calendar period.

How would one go about setting that up?

Accepted Solutions (0)

Answers (3)

Answers (3)

prasad_pisharam
Product and Topic Expert
Product and Topic Expert
0 Kudos

I think we can solve this situation through the settlement management functionality. using Condition contract process. we need to play around with the pricing routines. I have experienced this in one of my project. the minimum Royalty payout v/s the actual royalty payout.

pagarwal997
Participant
0 Kudos

Hi Prasad - I think we can do it too, just need to get creative. I like Thorsten & Anji's suggestions, we will try them both and let everyone know if it works.

thorsten_kraemer
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Pranay,

It has nothing to do with a value contract.

Just add a fixed amount condition to your contract and and use exclusion logic to control the payout.

Regards,

Thorsten

pagarwal997
Participant

I like this suggestion, we will try to set it up and get back to you.

Lakshmipathi
SAP Champion
SAP Champion
0 Kudos

From your post, it seems, irrespective of number of units sold, you need to pay $ 3000 per year, in which case, you can go with Value Contract

pagarwal997
Participant
0 Kudos

I don't think this would be the best approach for this case, since we will need to pay the vendor $1/unit when we invoice more than 3000 units.