Project Control – Sales for intercompany

andrj111
Explorer
0 Kudos
1,214

Hello,

I would like to check if there is a process of using Scope Item 4I9 (Project Control – Sales) in combination with 1MX Intercompany Sales Order Processing - (International).

Currently, when assigning WBS to the Sales Order item for another company's Plant, error KI100 (The CO account assignment object belongs to company code XXXX, not YYYY) is triggered.

In ECC PS world, SAP recommendation was to to use separate element for each CoCd, but it seems that in Project Planning app elements could be created only within one Company Code.

We have also looked at Scope Item 4AU Project Control – Intercompany, but as per description it's dedicated to Service process. Or may be someone used it for delivered items as well?

Thank you!

View Entire Topic
0 Kudos

Hi,

Projects with Revenue would be enhanced in the future with multiple company codes within the same project. The intercompany process documented in 4AU should then work for you.

Thanks.