on 2021 Oct 05 10:57 AM
Hi experts,
We have an issue regarding the production subcontracting flow at our customer.
Routing, bom, production version are all maintained. Also an inforecord is created.
But when the PR is generated it doesnt respect the leadtime of the inforecord even though it does find the inforecord. Any idea why this is happening?
The delivery date in the PR/PO is the start of the manufacturing order for some reason.
But the delivery date should respect the leadtime of 2 weeks as mentioned in the inforecord.
Purchase inforecord and delivery date are visible in the operations of the production order.
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
9 | |
7 | |
6 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.