on 2007 Jul 06 12:03 PM
Can anyone Explain about the Standard Scrap flow in the Production Order
Dear lakshmi,
In standard SAP we have nearly 4 types of scrp which affected our finish product order qty & its bom component req. qty. they can be chooses by us.
1. Assembly scrap :- it can be define in MRP 01 tab it increase finish product qty. so bom component qty increased automatically. Ex. if required qty. 100 & we give 5% assembly scrap then after mrp running we get plane order of 105 unit & bom component qty. respectively.
2. Component scrap :- It can be define in MRP 04 tab it not increase finish product qty. only increase bom component qty.
EX. Suppose a material A have its bom component B
Requirement of A is 100 unit & neaded 2 unit of B to create 1 unit of A then we needed 200 unit of B.
Now we put component scrap 5% so for completing requirement we needed 100 unit finish product for making which we needed 210 unit B i place of 200.
suppose 5% assembly scrap & 5% component scrap
100 unit requirement finish product 105 unit bom com 231 unit
3. Operation Scrap :- This can we apply in Routing operation detail.
It reduces the component for subsequent operation suppose we make 100 unit in operation 10 but if we put operation scrap 5% then we neaded to work only 95 unit in operation 20.
4.Operation Scrap with Net indicator:- It used to over come of operation scrap also applied in Routing or in production order for a perticular material so this material is neaded according to operation 20 qty in operation 10.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
9 | |
8 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.