on 2018 Nov 19 4:52 PM
Hi All,
I have a planned order scheduled with date and time.
When i convert this planned order into a production orders dates are copied from planned order, but time is not copied.
As per my understanding Production Orders date/time should be a copy of planned orders. Can you please help-me to understand what is happened here?
Steps to reproduce this scenario:
1. Create Planned Order (MD11)
2. Schedule Planned Order
3. Convert PLO in PRO (CO40)
Confguration. Detais:
Planned orders scheduling type = 3 Only Capacity Requirements
Production Order scheduling type = 3 Only Capacity Requirements
Regards,
Molina
Request clarification before answering.
Hi Flavio
If there are non-APO operations in your order, the time won' t necessarily match with the Production Order.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano.
I have same question, for pure PP (None APO. none ePPDS), is it possible to copy the un-dispatched planned order lead time schedule result (Date/time) to production order ?
We have a note 2633587 , guided how to inherit the BOM from planned order to production order, I am wondering why there is no simiar way for scheduling result.
Thanks
BR, Jerry.
Also, make sure that there is an entry in /SAPAPO/CP3 for in-house production where retransfer is set, otherwise, scheduled dates won't be sent back.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
125 | |
10 | |
8 | |
5 | |
4 | |
4 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.