Hi All,

I have a planned order scheduled with date and time.

When i convert this planned order into a production orders dates are copied from planned order, but time is not copied.

As per my understanding Production Orders date/time should be a copy of planned orders. Can you please help-me to understand what is happened here?

Steps to reproduce this scenario:

1. Create Planned Order (MD11)

2. Schedule Planned Order

3. Convert PLO in PRO (CO40)

Confguration. Detais:

Planned orders scheduling type = 3 Only Capacity Requirements

Production Order scheduling type = 3 Only Capacity Requirements

Regards,

Molina

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Flavio

If there are non-APO operations in your order, the time won' t necessarily match with the Production Order.


Regards,
Caetano

jerry_zhou02
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Caetano.

I have same question, for pure PP (None APO. none ePPDS), is it possible to copy the un-dispatched planned order lead time schedule result (Date/time) to production order ?

We have a note 2633587 , guided how to inherit the BOM from planned order to production order, I am wondering why there is no simiar way for scheduling result.

Thanks

BR, Jerry.

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Also, make sure that there is an entry in /SAPAPO/CP3 for in-house production where retransfer is set, otherwise, scheduled dates won't be sent back.