on 2024 May 22 11:42 AM
Hi, Experts.
I try to process Material Staging for production order in CO02, and Replenishment in /SCWM/STAGE.
Then Warehouse Tasks are created with the quantity defined in the following settings.
/SCWM/PSASTAGE
→Replenishment quantity for parts (30 EA)
Quantity in Production order :200
→Quantity in Warehouse task1 :30
Quantity in Warehouse task2 :30
Quantity in Warehouse task3 :30
・・・
I would like to create warehouse tasks with the production order quantity not replenishment quantity.
Quantity in Production order :200
→Quantity in Warehouse task1 :200
What customization should I look into?
Thank you in advance.
Best regards.
So Adachi
Request clarification before answering.