on 2019 Feb 11 8:53 AM
Hi
We have ML and actual costing for Make-to-Order scenario.
Every period, we do the actual costing and material ledger post closing. After the material ledger closing, the variances and adjusted on the consumption and factory output.
We are looking for a report, simiar to KKBC_ORD report, to display the input and output costs with the adjusted variance. In the KKBC_Ord we do not have the actual cost of each item (material and activities) adjusted with variance. (i.e. consumption of semi-finished goods are always shown at Standard Price). We want the consumption cost of the semi-finished input material with the actual cost (Standard Price +/- variance as posted in Material Ledger).
Is there a standard report ? Or we have to write it using the material ledger cost tables ?
Please guide me.
Request clarification before answering.
Hi Nikki
There is no standard report like that
CKM3N to some extent, but nothing like what you want
Writing your own report would make sense
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Ajay.
We will try to develop a report using the ML tables and Production Order tables.
User | Count |
---|---|
96 | |
39 | |
8 | |
6 | |
3 | |
3 | |
3 | |
3 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.