Hi co experts

while releasing billing document to accounting in T.Code VF02 it is showing error that no product costing estimate could be found

messege number ke380

i really appreciate for the early responce

regards

venkat

Edited by: venkataswamy bathini on Mar 14, 2009 10:43 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Venkat,

Pls check if there is Standar Cost released for that material available in the material master as on the date of billing.

If not, you need to run the Std Cost Estimate in CK11N, do Marking and Release in CK24.

You can use MR21 as an alternative.

Srikanth Munnaluri

Former Member
0 Kudos

Hi

i have estimated the cost in ck11n ,marked and released in ck24.

the std price will updating in meterial master.

i tried the tranaction in vfo2, but still getting same error

this is the Diagnosis

in copa the system tried to find a product cost estimate for product 44 in plant 1100 that uses costong variant dc08

the system lokked for the cost estimate using costing keys dcb as defined in the copa customizing settings

Regards

venkat

Edited by: venkataswamy bathini on Mar 14, 2009 12:36 PM

Former Member
0 Kudos

Hi Vankat,

Pls check the configuration settings you did regarding the "Costing Key" in COPA.

Costing Key is used to bring the Cost Estimate into COPA. Pls follow the path...

IMG -- Controlling -- Profitability Analysis -- Master Data -- Valuation -- Set Up valuation Using Material Cost Estimate..."Define Access to Standard Cost Estimate" (KE40). In this, you need to check the Costing Variant and Period Indicator. Pls check the Costing Variant, Plant etc in which you executed the Cost Estimate (CK11N), Marked and Released (CK24). The same should be assigned in this Costing Key.

Pls check and revert back for further assistance...

Srikanth Munnaluri

Former Member
0 Kudos

thanks a lot

problem solved

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi, The system tells that it need the Cost of the product at the time of billing as against the condition type VPRS. Hence, pl check the Masterial Master of the product and if the standard cost estimate is not there in Costing tab 2, you need to do Cost estimate thru CK11N and thru CK24 mark and release the cost estimate. Trust this helps much! Cheers!