on ‎2024 Feb 28 9:06 AM
Hi Gurus,
We have one material to which we have assigned X production version. This production version has recipe and BOM. The recipe has two resources say A & B. While creating the process order for this material as per standard process SAP should copy resource A & B into the order which are assigned to recipe. But every time on order creation only resource A got copy to order and resource B got automatically changed to C or D or any other resource. This is happening every time we create the order.
Can you please guide me what causing this error?