Dear All,

We have multilevel BOM configured in PC and using a Process Order and assigned two raw materials to semi finished material and semi finished material to finished product. But when we calculate variance, it is not showing variances, whereas variance key are properly maintained in the Material master.

Appreciate your input.

Thanks & Regards,

Santosh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check the control tab in Production/process order what variance key is assigned.

Then check in KKs2 by assign individual order & check.

Check for the date last confirmed also,sometime it may confirmed for the next month when you do variance it wont calculate any data.

Regards,

Raj

santosh_kavitkar
Contributor
0 Kudos

Variance key and other Product Costing settings are properly maintained in the Process Order.

Regards,