on 2015 Nov 07 12:18 PM
Hello!
I have one problem that some materials’ moving average prices (CKMLCR-PVPRS) are calculated wrong.
I think the problem resulting mistakes from assigning production costs.
What transaction or configuration (IMG path) I need to check to find and fix problem with calculation of CKMLCR-PVPRS?
I will be very apreciate for help, because I cant find information in help.sap.com.
Thank you.
Request clarification before answering.
Hi Max,
PVPRS field updated in CKMLCR table upon completion of Material Ledger Period End Closing Activities. It covers entire business process of Material Ledger. You need to understand how system calculate, updates price and analyze accordingly.
As you have mentioned you are suspecting discrepancy in production costs, you can use the transaction CKM3N to check the break up of cost for the price which is updated in CKMLCR table.
Further, if you suspect any difference in cost due to allocated costs, you can use CKMVFM transaction to look at value flow and reason for any unallocated or undistributed variances.
Once you have identified the reason for difference of expected value, you can resolve accordingly.
Hope this helps.
Regards,
Santosh Varanasi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello, I need some help.
I'm not finding a way to retrieve the value of the PVPRS field. Through material data and evaluation area. Can anyone give some direction.
Thanks.
Carlos
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for the answer!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 27 | |
| 25 | |
| 16 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.