on 2007 Jul 11 12:36 AM
Hi Gurus,
When I am checking capacity through MD04/ MS04, I get following error:
<b>No work centers with capacity requirements were found
Message no. MD305</b>
Diagnosis
The capacity situation is displayed for all work centers that are affected by the planned orders from the MRP list of the material.
<b>System response</b>
If no capacity requirements are created when scheduling the corresonding planned orders, no capacity situation is displayed.
<b>Procedure</b>
Check whether capacity requirements are created when scheduling planned orders. Capacity requirements are not created, for example, if the planned order was scheduled using the data in the material master record or if you switched off the creation of capacity requirements in customizing.
Please give me the solution.
Thanks in advance.
Shiv
Hi Shiv,
To generate capacity requirements there are the mandatory settings...
1) work scheduling view must be maintained.
2) work center capacities with formulas must be relevent for "finite scheduling" and capacity planning.
3) Controle key must have generate capacity reqs with scheduling indicator enable.
4) In planned order parameters OpU5 you must enable the indicator "generate capacity requirements with scheudling" with selection ID of routing.
While running MRP the scheduling mode must be 2 "lead time scheduling".
Regards
TAJUDDIN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
113 | |
8 | |
6 | |
6 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.