Popup when running MRP with MD01n "no planning file entry"

former_member254501
Active Participant
0 Likes
1,187

Hi All,

I am running MRP with MD01n but I get pop of no planning file entry exist ,But I have rum MRP for same material with MD02 multiple times.

Even after running MD01N with regenerativ planning same message pops up.

Checked in DBVM table entry exist there

Please guide If I am missing something here or this is standard behaviour.

Accepted Solutions (1)

Accepted Solutions (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi Harshal,

I simulated below two scenarios
Case 1 : MRP Run ( MD01N) with out selecting of the Regenerative Planning
Case 2 : MRP Run( MD02N) by selecting the Regenerative Panning.

In the Case 1 : I got the same message, as mentioned in the Incident
In the Case 2 : I got the error message( Attached below)

Root cause : This Material is mot maintained for the Plant, selected in the MD01N Screen
Just Take a look of the attached screen shot of these 2 Cases
Hope, this helps, kindly check & revert back, for further assistance, if required.
Thanks & Regards : Raja

KillerConfig
Discoverer
0 Likes
even though we maintain proper parameter still i am same error? is that related to Lot size?